Illustrative image – not actual.The offshore container terminal in Mumbai port is likely to be commissioned by December 2012.
Due to delays by the build, operate and transfer operator and dredging contractor, the Rs 1,400-crore project has been delayed. According to the licence agreement signed between the Mumbai Port Trust and Indira Container Terminal, the berth should have been commissioned long ago.
The project comprises 700 mtrs quay length in the Phase I extendable to 1,050 mtrs subsequently in the Mumbai harbour. The Mumbai Port Trust has appointed an independent engineer for approval of designs, quality control and monitoring progress of the operator. A project management consultant has also been appointed for preparation of estimates, tenders and supervision of works for the Mumbai port component.