Mumbai Monorail’s Phase-II to be further delayedIllustrative image – not actual.

The Mumbai Metropolitan Region Development Authority’s (MMRDA) Monorail project Phase-II which connects Wadala with Jacob Circle will be further delayed.

At present, only Phase-I of the Monorail between Wadala and Chembur is operational as MMRDA has only four working rakes.

The contractor, a consortium of Larsen and Toubro and Scomi Engineering (LTSE), is supposed to provide refurbished rakes in a phased manner. Two rakes were supposed to arrive in mid-November 2018, two in mid-December 2018 and two in mid-January 2019, but MMRDA has not received any.

Phase-II was expected to be commissioned in February 2019. The cost of refurbishing the spare rakes is said to be around Rs 20 crore.