Mumbai Monorail project cost exceededIllustrative image – not actual.

Mumbai Monorail corridor, under construction for nearly eight years now, has run into arbitration due to disputes between the contractor and the state over the project cost.

The MMRDA had originally expected to complete the 19.5 km monorail corridor, snaking its way from Chembur to Jacob Circle in Byculla through Wadala, by 2011. The second phase from Wadala to Jacob Circle is still underway with even the structural work yet to be completed.

The contractors and MMRDA had originally estimated the project cost to be Rs 2,700 crore for the entire line, amounting to Rs 138.5 crore per km. Until now, the MMRDA has paid about Rs 2,000 crore to the contractor.

The Mumbai Monorail project is being implemented by a consortium of India’s Larsen & Toubro and Malaysia’s Scomi Engineering on an engineering procurement contract model, where the government makes payments to the contractor in stages as per construction work. Both Larsen & Toubro and Scomi have separately submitted claims for cost increases in the project saying there has been a substantial delay from the government’s side, the contractors did not get land for the project on time as promised, and had to make several design changes due to unforeseen circumstances.

← All latest storiesBack to top →