Mumbai Metro One to start Versova-Ghatkopar Metro partiallyIllustrative image – not actual.

Mumbai Metro One (MMOPL) is likely to commission metro route running between Versova and Ghatkopar via Andheri partially due to issues related to Right Of Way.

 

MMOPL is likely to make a presentation to the MMRDA soon. In the presentation, the consortium has claimed that the metro will have to be commissioned partially. The test run is likely to begin by February 2012. If all permissions are obtained by the MMRDA on time, MMOPL can commission the stretch by April 2012. There are certain issues that is causing delay in the project. They are: an eight-metre road, which belongs to a private developer, some portion of civic land and shifting of a 110 kV transmission line of Tata Electrical Company, in Asalfa, the Maheshwar temple issue has to be sorted out, open setbacks of Azad Nagar, Versova and Ghatkopar metro stations are yet to be resolved.