The laying of tracks for both up and down lines of the BKC-Cuffe Parade section of the Mumbai Metro-3 project has been completed. On 08 December, 2024, Mumbai Metro Rail Corporation (MMRCL) announced the completion of 100 percent track laying stating that "this marks a significant milestone in the project progress towards full commissioning."
The 21 km-long section forms Phase-II of the project and is on track for commissioning before the next monsoon. The 12.5 km long Phase-I corridor (Aarey BKC) was opened for commuters in October. Phase-II has achieved an overall progress rate of 88 percent.
Station and tunnel construction have been completed 99 percent, with station construction at 97.6 percent. Work on systems and overhead catenary system (OCS) is nearing the 60 percent mark. One of the most challenging aspects of the underground Metro project lies in the construction of stations at Kalbadevi and Girgaum, which are densely populated areas with heritage structures, and old, dilapidated buildings. These areas have seen significant disruption, with 423 residential units and 289 commercial blocks affected.