Illustrative image – not actual.Oil & Natural Gas Corporation has entrusted a consortium led by Larsen & Toubro a fast-track order of installation of diversionary pipelines and associated platform modifications. Global Industries Offshore LLC of USA is partnering L&T in the project.
The project involves engineering, supply and commissioning of offshore facilities worth around Rs.325 crore. This is in addition to the main order of Rs.930 crore for pipeline replacement and platform replacement received earlier.
The additional scope involves 12 new submarine pipelines and 24 platforms to be modified, with completion targeted for pre-monsoon 2006.
ONGC's Mumbai High North platform, it may be recalled, was destroyed in a devastating fire on 26 July 2005. The total production loss was estimated at 1.2 lakh bpd of oil and 4.4 mmscmd of natural gas. ONGC has since partially restored production from the Mumbai High North field.