Illustrative image – not actual.The Mumbai High Court has dismissed
Dabhol Power Company’s writ petition challenging the Maharashtra Electricity
Regulatory Commission’s jurisdiction over DPC’s dispute with MSEB.
On 26 June 2001, a High Court Division
Bench directed MERC to decide question of jurisdiction within six weeks. The
Bench has however granted two week’s time to the DPC to appeal in the Supreme
Court while the direction to MERC would remain in abeyance.
The ad interim order issued by MERC
would remain in force until then, which means that DPC cannot proceed with any international
arbitration or take any steps to activate escrow accounts.