Mumbai-Ahmedabad bullet train to miss August 2022 deadlineIllustrative image – not actual.

The Indian Railways will miss the deadline of making the Mumbai-Ahmedabad bullet train operational by August 2022. The Railways is instead contemplating to open a shorter route of 50 km of the 508 km corridor of the project.

The National High Speed Rail Corporation (NHRSCL) has sighted various reasons leading to missing the deadline. A more realistic deadline of 2023 is being considered for the project.

The hurdles in execution of the bullet train project are not only confined to land acquisition. There are processes involved and the detailed planning, which are still underway.

The entire high speed rail corridor will require 1,434 ha of land with 353 ha in Maharashtra and the rest in Gujarat. This is divided into 7,000 plots, in 195 villages in Gujarat and in 104 villages in Maharashtra. The project covers three districts in Maharashtra and eight in Guajarat, besides a small area in Dadra and Nagar Haveli.

However, so far, only about 0.9 ha in Bandra-Kurla Complex has been physically handed over.

The project involves construction of the Vadodara station right on top of the existing station of the Indian railway network. A 220 mtr girder will be part of this station project. This girder could only be completed around the end of 2022.

It is likely that NHSRCL will miss the December 2018 deadline for land acquisition for the Rs 1.08 lakh crore project.