Illustrative image – not actual.The Mumbai-Ahmedabad Bullet Train project is progressing towards its expected first service in August 2027, with construction advancing at stations across the 508-km high-speed rail corridor.
In Mumbai, work at the Bandra Kurla Complex (BKC) station, the corridor’s starting point, is nearing completion for excavation and foundation activities. The station is being constructed nearly 30 mtrs. underground, making it one of the project’s most technically challenging sections. In Gujarat, the Surat station has reached a more advanced stage, with its structural framework and roofing completed. Inspired by Surat’s diamond-cutting industry, the station incorporates a design reflecting the city’s commercial identity. The corridor will connect Mumbai and Ahmedabad through Maharashtra, Gujarat and Dadra & Nagar Haveli, with 12 stations including Thane, Surat, Vadodara and Sabarmati.
Trains are expected to reach speeds of up to 320 kmph and cover the journey in around two hours. Operations may begin in phases, depending on construction progress across different sections.