The Mughal road in Jammu & Kashmir is expected to be inaugurated by September 2011, says sources. The road will serve as an alternative highway connecting the Kashmir Valley with Jammu region's Poonch district.

Hindustan Construction Company has been asked to speed up work on the 80-km stretch from Bafliaz (Poonch) to Shopian. The total cost of the project is Rs 639.85 crore, of which Rs 394.84 crore have been spent till date.

So far, 234 culverts have been completed out of proposed 428 being constructed on the road. As much as 40 km road length has been completed up to granular sub base level while 45 km taken up to water bound Macadam level.