MUDA is looking forward to completing the project within this fiscal year, once APMC allots the land. AMPC officials will hand over the land when they get the eight acre of land in return promised by MUDA, which the latter has set aside next to the APMC market yard.
The urban body is completing the 9.33 km of the ORR, but cannot accomplish it without taking up work on an 800 mtr stretch that passes through the APMC.
APMC has clarified that it wants the promised land and not the money. Although, MUDA has committed for exchange of land in order to complete the ORR project, APMC is uncertain. The district minister, V Srinivas Prasad, has stepped in and visited the site on 25 October, 2014. The minister announced that he would get the required clearance from the cabinet to complete the project by March 2015.
More Project Info:
Outer Ring Road (Mysore-Bannur Road-Mysore-Nanjangud Road) Project