Illustrative image – not actual.The MMRDA has an uphill task of acquiring land for the 22km Mumbai Trans Harbour Link (MTHL).
The MMRDA has official have inspected the proposed area and opine that the land acquisition for the project will be a huge task. The project will require land from the MbPT, CIDCO, SEZ which is under planning in the area, private land, forest land and even a portion of the railway land. It will also need some of the land of the NHAI for the construction. Approximately, it will require 10 ha on both sides (Sewri and Nhava Sheva) for the casting yard of the project.
There is an interchange near Sewri railway station and the MTHL alignment crosses the Pirpau jetty near Butcher Island. The distance between Sewri to Pirpau jetty is about 6.5km. The MTHL will also cross the ONGC oil and gas pipeline which is approximately 2km long. While the MTHL will require vertical clearance for the bridge from the highest high tide level of the sea, the project will also require safety clearance from the MbPT.