MSPL to implement steel project in phasesIllustrative image – not actual.

MSPL, the flagship company of the Baldota Group, will implement a 2.5 million tpa integrated steel plant at Hospet in Karnataka in phases.

In Phase I, the company will set up a facility to produce 1 million tpa of special steel, which will basically be automotive alloys, with an investment of Rs.4,300 crore. Completion of the first phase is expected by September 2009. Another 1.5 million tpa will be added by 2010, which will produce hot rolled flat products, entailing an investment of Rs.4,000 crore.

The company is still awaitng clearances for the second phase of the plant. The project will be implemented under its group company - Aaress Iron and Steel Ltd.