MSEB slaps yet another penalty on DPCIllustrative image – not actual.

Maharashtra State Electricity Board (MSEB) has slapped a penalty notice to Dabhol Power Company to the tune of Rs.400 crore, for irregularities in power supplies during February and March 2001.

 

According to MSEB officials, MSEB is willing to pay the April 2001 bill of Rs.139 crore on May 23, 2001. This would be the last payment made by MSEB, with the rest of the bills being settled against the penalty. During February 2001, MSEB had slapped a similar penalty on DPC (of around Rs.400 crore) for “misdeclaration” of power generation figures during January 2001.

 

The second penalty notice comes close on the heels of the Preliminary Termination Notice (PTN) served by DPC on 19 May 2001. As per the PTN, both MSEB and DPC have six months to come to some consensus, failing which the entire project may be shelved. In the event that the Enron project is shelved, MSEB may have to pay DPC an estimated Rs.17,000 crore.

 

It may be mentioned that the Enron Renegotiation Committee would be meeting for the second time on May 23, 2001. The first meeting held on May 11, 2001 (which was thinly attended) remained inconclusive.

← All latest storiesBack to top →