The trifurcation of the Maharashtra State Electricity Board (MSEB) into generation, transmission and distribution companies, is expected to cost Rs.4,500 crore, These funds would be used to supply quality power in the state.
Of the total amount, Rs.2,400
crore would be invested in maintaining the ratio between high tension and low
tension supply, Rs.750 crore would be used for shifting or addition of 750
transformers and setting up of substations and Rs.300 crore would be used for
metering purpose.
The restructuring of the MSEB
would result in accountability, auditing and also make room for cost and
responsible centers. It was also expected to result in getting constant minimum
returns on investment and make the three new companies more focused.
To effect the trifurcation, a Bill
would be passed within a month’s time.