Illustrative image – not actual.Maharashtra State Electricity Board (MSEB) has decided to go slow on wind power projects in the State following the on-going crisis of power purchase from Dabhol Power Company (DPC). MSEB owes a total of Rs.342 crore to DPC, which includes the bills for December 2000 (Rs.102 crore), January 2001 (Rs.127 crore) and February 2001 (Rs.113 crore).
MSEB, which has estimated a loss of Rs.3,706 crore during
2000-01, has stated that it was not in a position to buy power from wind power
projects and co-generation projects as the same was expensive.
According to MSEB, it would have to pay Rs.3.32 per
unit for power from co-generation projects and Rs.2.90 per unit for power from
windmills as against Rs.2.60 per unit for power generated from its own units.
MSEB also stated that if wind based power projects
were allowed to come up then it would lose its high tension industry consumers,
which would result in dual loss to it.
However, wind power producers have opposed the move
and asked the State Government to continue the policy formulated by the
previous Shiv Sena-BJP Government, whereby projects with a total installed
capacity of 450 MW of wind based power had been sanctioned for 2001.