Illustrative image – not actual.Maharashtra State Electricity
Board (MSEB) has approved a Rs.6.48 crore hike in value of the turnkey contract
awarded to KEC International for the completion of the Dabhol-Nagothane
transmission line. The earlier approved contract value was Rs.35.40 crore. The
rise in the contract value was due to an increase in the total number of locations
where costlier foundations in black cotton soil and dry fissured rock were necessitated
as per site conditions, besides an increase in tower protection quantity due to
hilly site conditions.
The number of foundations in black
cotton soil has increased from the estimated eight to 16 and that of dry
fissured rock from 119 to 333.75.
However, MSEB has not cleared the
Rs.5.5 crore sought by KEC International as compensation towards cutting of
trees along the transmission line, stating that the amount was unreasonably high.