Illustrative image – not actual.Maharashtra State Electricity Board (MSEB) and Dabhol Power Company (DPC) have entered into an agreement on the amount of power to be drawn from the first block of 722 MW of phase II of the power project during the test runs of the block. This is to help maintain MSEB’s monthly bill at Rs.150 crore.
According to the agreement, till the date of
commissioning of block I in June 2001, MSEB will draw around 100 MW each from the
phase II and block I of phase II. Further, if required the generation of phase
I can be dispatched to zero load by MSEB.
The two entities have entered into the above
agreement as MSEB, which is financially weak, is finding it difficult to pay its
dues to DPC on time. As of today, MSEB owes DPC Rs.102 crore for December 2000 and
Rs.127 crore for January 2001.