Illustrative image – not actual.Mumbai Railway Vikas Corporation has sought more funds from state government for slow paced Oval Maidan-Churchgate-Virar (OCV) elevated railway corridor project from the planning Commission in order to get the delayed project started.
The Corporation has asked for Rs 1,240 crore as a way to get the delayed project some pace. The total cost of the project is estimated to be Rs 22,500 crore.
The funds will be used to get rid away off, the unnecessary structures that are obstructing the way of the elevated corridor as well as of the underground utilities that could slow down the construction of pillar for the elevated bridge.
Shifting of underground utility deals with coordinating with 12 agencies which includes Reliance Power, Tata Power, BMC, MTNL, BSNL, GAIL, Mahanagar Gas and Western Railway itself in order to find alternative space for it.
Seeking of funds worth Rs 1,250 by MRVC from planning commission is a part of strategy used by MRVC to line up the private firms for the project.
Moreover due to delay in signing state support agreement between the corporation and state government, the tender process for proposed project is also getting delayed.