MRPL Phase III expansion by end 2011Illustrative image – not actual.

The Phase-III of Mangalore Refinery & Petrochemicals' (MRPL) refinery expansion in Dakshina Kannada, is expected to be commissioned by end-2011, ahead of its estimated commissioning schedule of March 2012.

The Phase-III project envisages increased capacity of crude throughput from 9.69 million tpa to 15 million tpa, an addition of a secondary processing unit for increased distillate yield by about 10 per cent and capacity, to process high TAN (acid) crude.

Necessary agreements have been signed with the licensors, after obtaining approvals from the Department of Industrial Policy & Promotions and Union Ministry of Commerce & Industries. Work is reported to be progressing satisfactorily on engineering packages.

Tendering process is underway for critical units - a 3 million tpa crude and vacuum distillation unit, hydrogen unit, captive power plant, crude storage tanks. The contract for the LPG bullets has been awarded. Land acquisition of 400 acres is almost complete and the 100 families affected by the project are presently being relocated.

Also See:

MRPL to open 25 retail outlets by end 2008 (28-Feb-08)

Related Links:
Project profile

← All latest storiesBack to top →