MRPL expansion stumbles on land rowIllustrative image – not actual.

Mangalore Refinery and Petrochemical's (MRPL) expansion project in Mangalore, Karnataka, has been stalled over a land row.

Owing to land dispute, the Rs 12,160-crore expansion may miss the January 2012 deadline for completion. MRPL is expanding refining capacity from 11.82 million tpa to 15 million tpa.

Persons displaced by Mangalore Special Economic Zone have blocked roads demanding better compensation, which has led to stalling of work at MRPL expansion project. MRPL is not part of the SEZ but has acquired 252 acre adjacent to the proposed 2,300 acre SEZ and therefore has been hit by the ongoing agitation. Around 16,000-17,000 labourers are not been allowed to enter project site because of the road blockage.