Illustrative image – not actual.The Madhya Pradesh government plans to invest Rs.2,815 crore in road projects connecting places of tourist and industrial importance in the state.
The tourist destinations proposed to
be connected are Mahakaleshwar, Kundalpur, Omkareshwar, Pachmarhi, Kanha,
Sanchi, Rahatgarh, Chitrakoot, Maihar, Bandhavgarh, Panna, Amarkantak and
Jabalpur.
Of the total investment planned,
Rs.1,051 crore would be utilised in constructing 1,961 km of roads under the build-operate-transfer
(BOT) route. The project is scheduled to commence on 15 October 2001 and will be
completed in three phases by June 2003. Contractors would have to maintain the
roads for a period of 15 years.
The first phase of the BOT project would
involve the construction of 982 km of roads with a proposed investment of
Rs.515 crore. Seven roads would be constructed under the first phase, while eight
roads would be constructed under the second and third phases.
The bridges and culverts in distress
condition on the state roads would be reconstructed, while those that are
submersible, will be raised. The road developer would have to maintain roads
within specified roughness index. The strengthening and reconstruction of roads
would be carried out by the National Highways Authority of India.