MP to invite bids for solar UMPP in 2015Illustrative image – not actual.
The Madhya Pradesh government is likely to start the bidding process for the 750 MW solar ultra mega power project (UMPP) from March 2015.


The 750 MW project would require an investment of over Rs 4,000 crore and will be developed on public private partnership (PPP).


The project will be set up in joint venture with Ministry of New and Renewable Energy, Power Grid Corporation and Solar Energy Corporation of India.


The ground work of clearances, approvals and the basic feasibility studies have already been completed .


13 ha of land spread over four villages of Barseta, Ramnagar, Latar and Badwaar has been chosen for the solar power plant in Gurh tehsil of Rewa district.


The government plans to execute the project in phases and the minimum size of the bid will be 250 MW. The entire 750 MW capacity is expected to be operational by 2017.


The project will be partly funded, around 50 per cent of the cost, by the World Bank, while the developer would have to invest the remaining share.

 

More Project Info:
Ultra Mega Solar Power (Gurh) Project

← All latest storiesBack to top →