Illustrative image – not actual.The joint venture company of the Railways and NTPC, Bharatiya Rail Bijlee Co is likely to sign a MoU for setting up a 1,000 MW captive power plant at Nabinagar, which is scheduled for completion by October 2007. NTPC will hold 74 per cent in, while the Railways will own the rest in the joint venture.
Railways require 2,200 MW for its entire network and currently pays Rs.4.22 per unit (average all-India) for its traction needs. With the setting up of this captive power plant, it will get power at Rs.2.51 a unit, which is 40 per cent cheaper. The cost per unit may further go down to Rs.2.39 if the joint venture gets mega-project status.
In February 2007, the CCEA approved a joint venture between NTPC and the Railways for setting up a Rs.5,352.5 crore inclusive of interest during construction of Rs.624.6 crore and working capital margin of Rs.103.1 crore thermal power plant at Nabinagar in Bihar.
NTPC will invest Rs.1,188.26 crore while the Railways will chip in with Rs.417.50 crore towards the equity.
Also See:
CCEA approval
for Nabinagar power project (2-Feb-07)
Related Links:
Project profile