Illustrative image – not actual.On 2 March 2008, the Nepal government signed a Memorandum of Understanding with Satluj Jal Vidyut Utpadan Nigam for developing a 402 MW Arun-III hydro electric power project, on build own operate and transfer basis (BOOT).
As per the MoU, SJVUNL will complete construction of the project within five years (60 months) after it receives necessary fund for implementation of the project. It will provide 21.9 percent of free electricity to the Nepal government every month when it starts generating power from the project in addition to royalty and export tax of the electricity.
Satluj will also reimburse Rs.451.4 million to Nepal government as the amount spent by the government for feasibility study of the project. It will also be responsible for constructing access road and transmission line as well as conducting environmental impact assessment of the project site.