Moser Baer has bagged five out of 14 hydro electric projects offered by the Himachal Pradesh government through the global bidding route with free power. All the 14 projects will have a  total generation capacity of 1,652 MW.

Moser Baer secured the 420 MW Reoli Dugli project with free power bid of 14.4 per cent, Seli (320 MW) with 14.41 per cent, Teling (69 MW) with 3.34 per cent, Miyar (90 MW) with 18.03 per cent, and Sach Khas (149 MW) with a bid of 13.13 per cent. All the five projects have an aggregate capacity of 1,148 MW.

Of the remaining nine projects, Jindal Steel and Power Ltd secured three projects, DCM Sriram Infrastructure won two, Patel Engineering and Delhi based ANS Construction Company won one order each.

Jindal Steel and Power Ltd won the 40 MW Lara project with a bid of 16.2 per cent, Kuling Lara (40MW) with 15.3 per cent and Mane Nadang (70 MW) with a bid 21.90 per cent.

DCM Sriram Infrastructure secured the 90 MW Khoksar project with a bid of 16.26 per cent and 81 MW Tinget with 17.26 per cent.

Patel Engineering Ltd has bagged the 236 MW Dugar project in Chamba with a bid of about 20 per cent and the 7.5 MW Kilhi Bahal in Kangra project was bagged by the Delhi based ANS Construction company.

 

 

 

 

 

 

 