The Ministry of Road Transport and Highways (MoRTH) has set up milestones for land acquisition procedures, and environment, forest and wildlife clearances for all national highways projects which come up for bidding with effect from 01 June, 2025.
The move will help synchronise the project approval, award and appointed date declaration activated by all the stakeholders and will help in avoiding delays in construction of national highway projects after award and prevent contractual disputes as well as time and cost overruns, the Ministry said in a recent notification.
As per the notification, environmental clearance, wildlife clearance, general agreement drawings of Railways and utility shifting estimates have to be in place before bids are received, while the general agreement drawings of the Inland Waterways Authority of India (IWAI) has to be completed before inviting the bid and the forest clearance have to be completed before issue of letter of award.
For land acquisition, however, it has notified that over 90% of right of way (ROW) length for the project has to be acquired before receipt of bids. Road transport minister Nitin Gadkari, in response to a question in Rajya Sabha in December, said nearly 44 percent of national highway projects, each worth at least Rs 150 crore, across 32 states and union territories (UT), were under construction as of March 2024, but are facing delays.
According to Unnion Minister Nitin Gadkari, 419 out of 952 such projects had missed their original completion deadlines by March 2024, with delays at various stages of project completion, due to land acquisition bottlenecks, delays in obtaining statutory clearances and permissions, utility shifting, encroachment removal, and law and order issues. Maharashtra had the highest number of delayed projects, with 59 out of 101 projects running behind schedule, he had said, adding proportionally, northeastern states and UTs are the worst affected.