Illustrative image – not actual.
The project needs to be implemented on EPC mode, under NHDP Phase-IV, in Punjab.
The scope of work is as follows:-
i) Widening & strengthening of existing two-lane carriageway to four lane with paved shoulders of Harike-Zira-Faridkot section of NH-15 (new NH-54) from existing km 166.925 to km 221.380 including construction of Zira, Talwandi & Mudki bypasses in Punjab. The estimated cost is Rs 680.68 crore, with a completion period of 24 months and maintenance period of four years
ii) Widening & strengthening of existing two-lane carriageway to four lane with paved shoulders of Faridkot-Kotkapura-Bathinda section of NH-15 (new NH-54) from existing km 221.380 to km 283.000 including construction of combined Faridkot-Kotkapura bypass in Punjab. It is estimated to cost Rs 686.06 crore. The completion period is 24 months and maintenance period is four years
More Tender Info:
Widening & Strengthening of NH-15 sections in Punjab
More Project Info:
Road Upgradation (Faridkot-Kotkapura-Bhatinda) Project