Illustrative image – not actual.The project cost was brought down to Rs 310 crore from Rs 350 crore, in line with the cost incurred on dredging by ports in India in the last two years.
The private player will be responsible for dredging the channel and then maintaining it for 15 years.
The scope of work for the project involves the draft of MPT’s navigation channel from the existing 14.5 mtr to 19.5 mtr, which will help the port to service large cape size ships of 1,75,000 DWT (deadweight tonnage). At present, MPT can handle only 75,000 tonne vessels.
Among other key projects, MPT is in the process of floating a Rs 520 crore tender on PPP basis for conversion of mechanical iron ore handling berth to general cargo handling.
More Project Info:
Approach Channel Deepening Project