Illustrative image – not actual.South Eastern Railway conducted a trial run of a diesel engine on the Tamluk-Nandakumar section (upto the Haldi bridge) of the Tamluk-Digha broad gauge railway line in West Bengal.
The longest and most critical block section (23 km) between Nandakumar and Bajkul has been completed.
Construction of the bridge over the Haldi river had been one
of the major bottlenecks in completion of the section. The bridge consists of
11 spans of 150 feet steel girders. Girdering of the bridge was completed in December
2000 in a record time of five-and-a-half months. The cost of the bridge is estimated
at Rs.11 crore.