Illustrative image – not actual.About 1,500 MW of coal based power capacities are slated to commence power generation at Mundra in Gujarat by June 2011.
The capacities include coal based power generation capacities of Adani Power (660 MW) and Tata Power (800 MW) at Mundra based on supercritical technologies.
Adani is in the final stages of commissioning their Unit II of 660 MW super-critical unit in Mundra. The trial generation from the unit is likely to begin by end-May 2011 or June 2011. With this, the capacity of the Mundra unit of Adani Power will reach 2,640 MW. Further, Tata Power's 800-MW unit of ultra-mega power project may be ready for trial generation in a month. The 4,000-MW (5x800 MW) project is undertaken by Coastal Gujarat Power, a wholly owned subsidiary of Tata Power.