The UNDP-GEF (Global Environmental Facility) funded coal bed methane development project undertaken by Coal India at Moonidh-Sudamdih in Jharia coalfields in Jharkhand, is expected to be completed in 2007.

Originally slated for completion in five years, the project has undergone several rounds of revision in time schedule and project specifications. It is learnt that the delay was caused mainly due to lack of experience and difficulties in procuring equipment.

The project aims generating one MW gas-based power for internal consumption at Moonidih and setting up a CNG station at Sudamdih for refuelling of approximately 50 dumpers, trucks or other such motorised mining equipment.