Illustrative image – not actual.The services on Monorail Phase-II between Wadala and Mahalaxmi will not start before March 2019. The services on Monorail Phase-I commenced between Chembur and Wadala on 1 September 2018.
The delay over starting the services on Phase-II Monorail despite having safety clearance is due to shortage of functional trains.
Out of the total 10 trains only four are functional. Mumbai Metropolitan Region Development Authority (MMRDA) will commence operations only after around seven to eight trains are functional by February 2019.
Out of the four trains currently, three trains are operational, and one train is on standby for emergencies. These three trains are currently able to maintain a frequency of 15 minutes, but if Phase-II has to be made operational, and also maintain frequency of around 15-20 minutes, it will require at least seven trains.
One Monorail train has four coaches and MMRDA anticipates the ridership to go up to around one lakh passengers daily from the present around 15,000 passengers daily for Phase-I.