Monnet Industries to set up integrated steel plant at HazaribaghIllustrative image – not actual.

Monnet Industries has plans to set up an integrated steel plant at Hazaribagh in Jharkhand with an investment of about Rs.1,400 crore. 

 

The company proposes to spend Rs.200 crore on a sponge iron plant and another Rs.150 crore to set up a ferro alloy plant. Iron ore and manganese for the project would be procured from the new mines in and around Chaibasa in West Singhbhum district of the state. The integrated steel plant would run on electrical energy and would have ‘arc’ furnaces.

 

The project would include the setting up a coal washery at the Pakri Barwadih block of Hazaribagh and a 35 MW captive power plant. The captive power plant would be set up in 2 sections of 25 MW and 10 MW. The 10 MW section of the power plant would run on waste coal.

 

Monnet Industries is awaiting the a no objection certificate from the Central Government for undertaking mining and for setting up the steel and power plants.

 

The whole project, which is expected to take 9 months to complete, would provide direct employment to at least 10,000 people and add an annual revenue of Rs.220 crore to the state exchequer.

 