Monarchak power plant to start in January, 2015Illustrative image – not actual.
The 101 MW gas based thermal plant at Monarchak in Sipahijala district of Tripura would start generation in January, 2015.

 

By the first week of January, the supply of natural gas to Monarchak plant would begin. This is the second power plant to be started in Tripura after the inauguration of the second unit of the 726 MW gas based thermal power project by Prime Minister Narendra Modi at Palatana on 1 December, 2014.

 

The North East Electric Power Corporation (NEEPCO) has completed the entire commissioning work of the Monarchak power project. The power generated from this unit will be utilised in Tripura.

 

For over three months, the project was ready for testing but it got delayed due to hydrocarbon charging equipment from ONGC. This small piece of equipment would cable the underground gas pipeline travelling under rivers and other water bodies to the project site from the ONGC station. The equipment is expected to arrive by 15 December, 2014.

 

More Project Info:
Monarchak Power Project

← All latest storiesBack to top →