The board of directors of MOIL has given nod to two projects, including doubling the output from Balaghat mine in Madhya Pradesh. 

The board has recommended the project of sinking of high speed vertical shaft at company's Balaghat Mine. The production is expected to increase from 4,50,000 tonne per annum to 8,00,000 tpa through the project.  The production is expected to increase gradually from 2015-16. 
 
Also, the board approved another project for deepening of vertical shaft at Chikla Mine to sustain the present capacity of 80,000 tpa.  The project in Maharashtra is scheduled to be completed in 2015-16. 
 
MOIL intends to increase output to 1.5 million tonne from the existing 1.1 million tonne by 2015 through an investment of Rs 768 crore. The company will be investing Rs 1,200 crore to increase its total production capacity to 20 lakh tonne by 2020. 