MoF plans mixed fee structure for infra project consultantsIllustrative image – not actual.

The ministry of finance (MoF) has proposed that consultants for infrastructure projects, executed on public-private partnership (PPP) model, should be awarded contracts on the basis of a mix of upfront fee and success fee-based mechanism.

It has been contended that an upfront fee will incentivise preparation of a well-researched project report while success fee will ensure the project gets structured in such a manner that it is successfully bid out.

Questions have been raised on the success fee-based mechanism too. It is said that since the fee, which could be computed as a percentage of total capital costs, will be given after the project has been successfully bid out, there is ample scope for consultants to jack up costs in the project report.

It is learnt that a dual mechanism, wherein a part of the fee is paid as a fixed sum and part of it as success fee, has been proposed as an interim method for hiring consultants.

At present, there are three modes being followed by sponsoring authorities in the centre and state governments for developing PPP projects in the infrastructure sector: hiring consultants through competitive bidding and forming a joint venture with one of the project development companies and awarding development work for all projects to this company on a single tender basis. A third method followed is development of projects by a consultant where the payment to the entity is a success fee, recoverable from the successful bidder.

The JV route is being followed by states such as Rajasthan. Under the method, the identified partner charges the state government a fee known as 'actuals', which is expected to cover only the actual amount spent in developing a project. The finance ministry has pointed out that in such cases, the JV partner takes from the government large sums of money without being subjected to the cost analysis of the term 'actuals'.