MoEF to delink green nod for thermal power projects Illustrative image – not actual.

The Ministry of Environment & Forests (MoEF) is looking forward to delinking green clearance for a host of large thermal power projects from those for captive coal mines attached to them.

 

The ministry has offered special dispensation to ultra-mega power projects (UMPPs) by delinking their environment clearance (EC) and forest clearance (FC) of their captive coal blocks.

 

At present, work on end-use projects (cement, steel, power) can commence only after the two green nods - EC and FC - are sanctioned to both, projects and the respective captive mines.

 

In the case of UMPPs, these clearances will be granted to those coal blocks that do not fall under the category of inviolate forest areas, such as tiger reserves and wildlife sanctuaries. Currently, EC for UMPPs - each above 4,000 MW - are not given till the time the captive coal block secures these statutory clearances from the MoEF.

 

The delinking of EC and FC clearances for projects and captive coal mines will not apply universally, but the ministry will entertain applications from the developers and give such clearances on a case-to-case basis. This will ensure that projects of only serious players get this relaxation.

 

Recently, the ministry granted such delinking to Bedabahal UMPP in Orissa to allow the bidding process for the 4,000 MW project to be completed in FY14 even while EC for the project's captive mines comes later. The project was allocated three coal blocks, of which Minakshi B and dipside of Minakshi fall in the prohibited region considered too green and called 'no-go' area by the environment ministry to permit mining.