MoEF sends show cause notice to VedantaIllustrative image – not actual.

The MoEF has served two notices to Vedanta Aluminium's (VAL) Lanjigarh refinery in Orissa.

According to sources, in the latest notice, the MoEF has asked VAL to explain why environmental clearance given to its one million tonne refinery in Lanjigarh should not be withdrawn and the refinery shut down.

The company has gone ahead for a six-fold expansion of the refinery from a production capacity of one to six million tpa. It had filed for an application for expansion in August 2007. The terms of reference for a detailed impact assessment study were given in February 2008. The final report was submitted by the company in June 2009. However, the Environment Appraisal Committee (EAC) had asked for additional details. It had also undertaken a site visit, which after several postponements took place in July 2010. The expansion proposal is yet to be cleared by the EAC.

In its show cause notice, the ministry has cited reports that the refinery has encroached and enclosed 26 ha of forest land within its boundary. The plant was given environmental clearance in September 2004, on the condition that it did not require any forest land. Its illegal enclosure of forest land and the construction of a road using forest land invalidate the clearance.

VAL has time till 14 September 2010 to submit its reply. An unsatisfactory explanation is likely to result in the refinery's closure.

In August 2010, the MoEF had rejected VAL's bauxite mining project proposed in Niyamgiri Hills citing defiance of environment norms.