Illustrative image – not actual.The Union MoEF gave environmental clearance to NTPC's 2x660 MW supercritical technology based Mauda Stage-II coal based power plant in the Nagpur district of Maharashtra. The project entails a cost of Rs 6,745.29 crore.
The water requirement for the proposed plant will be 40 cusecs, which will be met from Hosikurd Dam on Wainganga / Kanhnan river at a distance 24 km from the site. Besides, a total of 7.85 million tpa of indigenous coal will be supplied from Mahanadi Coalfields.
This project is an expansion of the under-construction 2x500 MW Stage-I project.