Illustrative image – not actual.The MoEF has granted clearance to Rosa Power Supply Company, a subsidiary of Reliance Power, for its Phase II - 2x300 MW Rosa thermal power plant being developed at Chaudhera in the Shahajahanpur district of Uttar Pradesh.
Around 210 ha is required for the project, of which 195 ha is available at the existing site. The water requirement is pegged at 20.42 cusec and is likely to be sourced from the Garrah River. Meanwhile, the power plant has been granted coal linkage from Central Coalfields, which is expected to meet the coal requirements of 2.7 million tpa for this phase.
The MoEF has also cleared a 52 MW expansion project being developed by Reliance Energy in Zuarinagar, Goa. The expansion project is to come up on 12.83 ha in the existing plant premises and will operate on natural gas and naphtha.
Also See:
R-Power achieves closure for Phase II Rosa plant (29-May-09)