Illustrative image – not actual.The Union Ministry of Environment & Forests has given clearance to Reliance Industries' 800 MW gas-based combined cycle power plant in the Raigad district of Maharashtra. The project entails an investment of about Rs.3,200 crore.
The project will run on 3.6 mmscmd of gas, which will be sourced from RIL's Krishna-Godavari basin. However, the gas will initially be transferred to the site via the envisaged 140 km long East West Pipeline through Andhra Pradesh, Karnataka, Maharashtra and Gujarat which RIL is currently in the process of setting up. Subsequently, the gas supplies will reach the plant via GAIL India's network of Dahej-Uran-Panvel-Dabhol and Ambewadi-User gas pipelines.
The total land requirement for the project is around 90 acres. The 24.9 MLD m3/day water requirement for the project will be sourced from the Maharashtra Industrial Development Corporation.
Related Links:
Project profile