MoEF clearance for three power projects in SikkimIllustrative image – not actual.

The MoEF has given nod for continuation of survey and investigations for Sikkim government’s three mega power projects out of six in North Sikkim that had been stalled following reports submitted by Centre of Inter-Disciplinary Studies of Mountains and Hill Environment (CISME) in 2009.

The MoEF has given a go ahead for continuation of survey and investigations for Teesta Stage I (280 MW), Teesta Stage II (330 MW) and Lachung (99 MW) projects. The approval has come up after the reports submitted by the Expert Appraisal Committee that had inspected the proposed power sites above Chungthang in North Sikkim.

However, the permission has come with a rider for these power projects. In case of Teesta Stage I power project, the MoEF stated that the permission is only to facilitate geological investigations and hydrological studies and that the project authorities should revert to the MoEF before they undertake preparation of Environment Impact Assessment/Environment Management Plans reports. Similar conditions have been imposed on the Teesta Stage II and Lachung projects.

The state government and project developers are yet to receive clearance from the MoEF for the remaining three projects of Bhimkyong (99 MW), BOP (99 MW) and Lachen (120 MW).

← All latest storiesBack to top →