Illustrative image – not actual.The Ministry of Environment & Forest clearance for Narmada Valley Development Authority's Rs.2,000 crore Indira Sagar lift irrigation scheme is expected by August 2008.
The implementation of the project, especially the laying of the pipelines, will require 87.18 ha of forest land. It will be compensated with alternative land identified in Aswaraopet mandal. The pump house construction at the off-take point of the scheme will be completed by August 2009.
The project was expected to help irrigate over two lakh acres of land in Khammam, Krishna and West Godavari districts.