Illustrative image – not actual.The MoEF on 1 July 2011 allowed safety and electricity works up to 200 MW at
Alaknanda Hydro Power Company’s (AHPCL) hydel power project in Uttarakhand.
However, the minister refused to lift the stop-construction order.
The stop work order was issued by the ministry based on Uma Bharati’s, former
Madhya Pradesh Chief Minister, representation that the project will result in
submergence of the Dhara Devi temple in the Srinagar valley.
As part of the new order, the ministry has asked AHPCL to prepare a modified
plan to preserve the religious sanctity of the temple and examine how the part
of the rock on which the platform of the deity has been constructed and the one
that formed its backdrop maintain contact once the rock is elevated. Also, the
company will have to construct walls over a length of one km at the dam,
de-silting basin and power house. The detailed action plan along with bank
guarantees of R1 crore is to be submitted to the state pollution control board.