The Union Ministry of Coal (MoC) has threatened to cancel the allotment of Paturia and Gidhmuri coal blocks in Chhattisgarh, which were allocated to Chhattisgarh State Electricity Board (CSEB).

CSEB has been unable to clarify about any significant progress over the last five years, despite several stiff warnings and show cause notices from the MoC.

According to the ministry, the company has yet to obtain the forest and environment clearances and mining lease, and complete the land acquisition process. As a result, the company has failed to start production, which was expected to commence in May 2008. However, the company has now committed to start production by September 2010.