The project worth Rs 374 crore will be undertaken on private public partnership (PPP). In June 2015, Hyderabad-based MNR Educational Trust was appointed contractor for the project. The project, however, faced delays in land acquisition and hence remained in planning stage.
In September 2018, land was allotted for development of the project.
The Maharashtra Pollution Control Board accorded approval for the project in March 2019. The work was expected to commence by October 2019.
In January 2020, MNR Educational Trust received environment clearance (EC).
As per data mapped by Projects Today, work on the project is expected to commence by April 2020. The completion is scheduled for April 2021.