MMRDA's monorail sub-station project faces roadblockIllustrative image – not actual.

MMRDA is yet to solve the major issue of the land patches for erecting the electricity traction sub-stations for the monorail project in the city.

These sub-stations are the vital part of the monorail system, and they are to provide electricity to the coaches. Some of the land patches that are needed in the Phase II of the monorail are located in areas like Lower Parel, Parel, Sewri, Naigaon and Matunga. The MMRDA needs 1,086 sq mtrs in Naigaon, 239 sq mtrs in Parel, 750 sq mtrs in Lower Parel and 117 sq mtrs in Matunga.

The MMRDA has sought these land patches from the BMC. However, the BMC has, so far, not responded to the same. Meanwhile, the MMRDA is exploring whether these sub-stations can be constructed at the site of the monorail stations, instead of building them elsewhere.