Illustrative image – not actual.MMRDA is likely to finalize the bid documents for Phase-I of the Mumbai Metro Rail project by 17 January 2006.
The final bidders for the project are three consortiums led by Reliance Energy, Siemens India and IL&FS. The project will be constructed on BOT basis and is expected to achieve financial closure by June 2006. Technical bids were evaluated in early 2005.
Work on the Phase-I is likely to commence by 2006 and scheduled for completion by 2013. Phase-I of the project will cover three corridors connecting Versova-Andheri with Ghatkopar on a 15 km raised rail corridor, expected to be completed by 2008.
Metro rail project (Phase-I), expected to cost Rs.1,500 crore, has been conceived as a joint venture project in which the government and the private promoters of the project will hold 13 per cent equity each, putting Rs.190 crore each.
The remaining 74 per cent will be financed through debt, to be raised through market borrowings and a SPV is being created for this purpose.
The state government's exposure to the Mumbai Metro's first phase is likely to be around Rs.800 crore, taking into account the cost of land to be provided by the government for a depot at Versova and the viability gap funding, which will be offered to the private operator. Of the government's share, MMRDA is likely to bring in other service providers in the city such as BMC and BEST while retaining 50 per cent of the equity for itself.
The 36-km long Phase-II will connect Colaba with Charkop in Kandivili via Bandra and around 12 km of this corridor will be underground. The 12.8-km long third corridor will be entirely underground, connecting Mahim to Mankhurd through the Bandra-Kurla Complex.