Illustrative image – not actual.The Mumbai Metropolitan Region Development Authority (MMRDA) has terminated contract with Simplex Infrastructures for Metro 2B over delays.
The company commenced work on the Metro in November 2018 on a 12 km long viaduct from DN Nagar to Bandra Kurla Complex (BKC), and 11 stations.
MMRDA has also served termination notices to RCC-MBZ which was executing the section of the corridor between BKC-MTNL and Chembur, and the car depot for the corridor at Mandale.
Simplex Infrastructures had completed only around five percent of the work, while RCC-MBZ had completed around four percent of the viaduct and six percent of the carshed work since 2018. The corridor is expected to be commissioned by 2022.